This project was for the design of the reconstruction of American Bridge Way for approximately 900 lineal feet that is heavily used by adjacent properties with significant tractor-trailer vehicle traffic. Construction plans that were developed incorporated a methodology of maintaining uninterrupted access to the businesses with phasing of construction and minimal short-term detouring requirements. Additionally, project scheduling had tight time constraints with notice to proceed for design to substantial completion of construction of an overall project duration of three months.